I have done a fair bit of timber engineering, but I am not quite sure how to ACCURATELY calculate the shear value of an 8x8 HF2 p.t. post that has been spliced with a 7/8" diameter x 24" long threaded rod, embedded 12" into the center end of each abutting post.
My task is basically to develop a splice that will be as strong as the 8x8 post was unspliced. I have the moment connection taken care of with straps on all sides.
The post already has this 7/8" rod in the center, so I need to know what the shear value of it is.
If you cannot help me do this, please do not suggest other ways of making the connection. That is out of the question at the moment.
Thanks,
My task is basically to develop a splice that will be as strong as the 8x8 post was unspliced. I have the moment connection taken care of with straps on all sides.
The post already has this 7/8" rod in the center, so I need to know what the shear value of it is.
If you cannot help me do this, please do not suggest other ways of making the connection. That is out of the question at the moment.
Thanks,