Baldie
Geotechnical
- Apr 23, 2003
- 15
I am concerned about removing sheet piling that will be installed in an existing embankment dam to function as a cofferdam while the intake is replaced. The main concern is that the soils will be disturbed when the sheet piles would be removed after construction and that seepage through the embankment could be increased due to the loosened soils, possibly adversely affecting the stability of the dam. (Stability analyses have not been done yet, but are likely to yield low safety factors for a drawdown condition of the downstream reservoir--the downstream face is currently partially submerged from an adacent reservoir.) It also might just be bad practice to drive sheet piles into an embankment dam and then remove them. On the other hand, I don't want to be overly conservative resulting in a costly design.
Generally, the foundation soils are fairly clean sands, typically with less than 10% passing #200. Embankment fill soils are also granular, but range from clean to clayey sands. Interlensed claystone and sandstone bedrock is about 40 feet deep. The dam is considered low hazard. Seismicity in the area is very low. A seep exists at one groin of the dam and is believed to be due to a cobble layer in the foundation located just below the embankment fill.
I have been unable to find any literature on the amount of disturbance to expect if sheet piles are removed. Of course, we could recommend that the piles be left in place, but they would need to be cutoff near the bottom of the reservoir which could be costly to do underwater. Another possibility would be to grout as the piles are removed. Yet another possibility is to make the contractor responsible for restoring the integrity of any loosened embankment soils. (This makes sense because the type of cofferdam and installation procedures will affect the amount of disturbance, but it goes back to the same question of how much disturbance would there be.) I would appreciate anybody else's similar experiences or suggestions. Following are some more details of the project:
As part of a repair to an outlet pipe through an existing embankment dam, a contractor will be required to design a cofferdam to replace the inlet so that work can proceed in the dry. It is not possible to completely drain the reservoir because of operations.
My task as the geotechnical design engineer is to comment on the feasibility of different cofferdam designs. Cellular, sheet pile, or double sheet pile walls all appear to be feasible. The intake is a morning glory type (vertical CMP) located near the upstream toe that will be replaced. A contractor will probably elect to use some type of sheet pile system because the construction limits are relatively small. We envision that a u-shaped configuration will be used with the open end in the upstream embankment slope and the end of the piling near the upstream crest shoulder. The parallel walls would be on the order of 20 to 25 feet wide.
Generally, the foundation soils are fairly clean sands, typically with less than 10% passing #200. Embankment fill soils are also granular, but range from clean to clayey sands. Interlensed claystone and sandstone bedrock is about 40 feet deep. The dam is considered low hazard. Seismicity in the area is very low. A seep exists at one groin of the dam and is believed to be due to a cobble layer in the foundation located just below the embankment fill.
I have been unable to find any literature on the amount of disturbance to expect if sheet piles are removed. Of course, we could recommend that the piles be left in place, but they would need to be cutoff near the bottom of the reservoir which could be costly to do underwater. Another possibility would be to grout as the piles are removed. Yet another possibility is to make the contractor responsible for restoring the integrity of any loosened embankment soils. (This makes sense because the type of cofferdam and installation procedures will affect the amount of disturbance, but it goes back to the same question of how much disturbance would there be.) I would appreciate anybody else's similar experiences or suggestions. Following are some more details of the project:
As part of a repair to an outlet pipe through an existing embankment dam, a contractor will be required to design a cofferdam to replace the inlet so that work can proceed in the dry. It is not possible to completely drain the reservoir because of operations.
My task as the geotechnical design engineer is to comment on the feasibility of different cofferdam designs. Cellular, sheet pile, or double sheet pile walls all appear to be feasible. The intake is a morning glory type (vertical CMP) located near the upstream toe that will be replaced. A contractor will probably elect to use some type of sheet pile system because the construction limits are relatively small. We envision that a u-shaped configuration will be used with the open end in the upstream embankment slope and the end of the piling near the upstream crest shoulder. The parallel walls would be on the order of 20 to 25 feet wide.