Stymied
Civil/Environmental
- Jun 20, 2004
- 4
I fess up that I am not an engineer. I own a channel lot. 70' of channel frontage. Steel sheetpile wall, clay soil, 24" by 12" sheetpile deadmen every 10 feet 18' back from wall. Two 3/4" tie rods from sheetpile wall welded to each deadman, unfortunately not threaded and bolted. Metallurgical report shows welds weakened tierods and/or deadmen, causing low cycle fatigue and failure. Sheetpile wall was noticed bowing out in early January, 2004.
February 20, 2004 a water line at the dock broke and spewed 18,000 gallons of water over an 18 to 24 hour period of time. Question 1) How does one calculate the amount of pressure or force that this amount of water would have put on the already failing wall? Question 2) Would a properly constructed seawall have been able to withstand the pressure of 18,000 gallons of water spewing behind it?
Thanks for your help.
February 20, 2004 a water line at the dock broke and spewed 18,000 gallons of water over an 18 to 24 hour period of time. Question 1) How does one calculate the amount of pressure or force that this amount of water would have put on the already failing wall? Question 2) Would a properly constructed seawall have been able to withstand the pressure of 18,000 gallons of water spewing behind it?
Thanks for your help.