DEL2000
Structural
- May 10, 2004
- 48
I asked a question the other day about getting loads on a crane outriggers . . . well, now I am shoring for that crane to drive out onto the slab it is going onto, as well as shoring for the outriggers.
I haven't done a lot of shoring, so I don't know if I am missing something obvious . . . it seems impossible to shore the slab and use the slab at all to distribute the load if it doesn't have negative reinforcement. I have one way slabs spanning 13', so any line of shoring added in the middle of that slab won't have negative moment steel (The negative moment steel is cut off at the quarter points of the slab as that is all that is required for the building in its completed state).
What are the options here? Does the contractor have to put steel in the top of the slab now? Or do you have to put enough shoring in there that the concrete is in straight compression, transfering load straight to the shoring? This second option would seem too problematic that I haven't even suggested to the contractor, but maybe it is better than adding reinforcement in the top of the slab and having to worry about the detailing of the rebar and all of that added cost.
We mentioned limiting where he could drive the crane on the slab and provide shoring directly beneath where he was going to drive . . . they rightfully didn't want to be limited in where they could drive the crane if they get out there and had to move the crane this way or that way, they didn't want the whole job shut down.
Just looking for some ideas from somebody who may have come across this situation.
I haven't done a lot of shoring, so I don't know if I am missing something obvious . . . it seems impossible to shore the slab and use the slab at all to distribute the load if it doesn't have negative reinforcement. I have one way slabs spanning 13', so any line of shoring added in the middle of that slab won't have negative moment steel (The negative moment steel is cut off at the quarter points of the slab as that is all that is required for the building in its completed state).
What are the options here? Does the contractor have to put steel in the top of the slab now? Or do you have to put enough shoring in there that the concrete is in straight compression, transfering load straight to the shoring? This second option would seem too problematic that I haven't even suggested to the contractor, but maybe it is better than adding reinforcement in the top of the slab and having to worry about the detailing of the rebar and all of that added cost.
We mentioned limiting where he could drive the crane on the slab and provide shoring directly beneath where he was going to drive . . . they rightfully didn't want to be limited in where they could drive the crane if they get out there and had to move the crane this way or that way, they didn't want the whole job shut down.
Just looking for some ideas from somebody who may have come across this situation.