tolind
Civil/Environmental
- Aug 19, 2003
- 30
My head engineer is out of town and I got some problems.
I recently submitted a Short-Circuit Calculation to a City for permits. They asked specifically for it so I worked it out according to the Cooper Selecting Protective Devises book. I have an existing 300KVA 208v 3phase Transformer that leads to a meter and then leads into an existing 1000A 208v 3phase fusible distribution panel. When Calculated I have a I(sc sym rms)=74,426A.
The City planner says that this is an extremely high number and that I need to indicate the Let Thru Current (which I thought was the 74,426A) and need to indicate how I am protecting against this. With every other project I've worked on I have never had any questions in regards to this.
Secondly, He also states that I need to indicate the existing load on existing panels that are gaining circuits. I understand why he would want this(to show that I am not overloading the panels) but how can I figure this out when half the circuits are being removed in the field and most are just receptacle ciruits anyways.
Thank you for any help, I always receive great information from this site.
I recently submitted a Short-Circuit Calculation to a City for permits. They asked specifically for it so I worked it out according to the Cooper Selecting Protective Devises book. I have an existing 300KVA 208v 3phase Transformer that leads to a meter and then leads into an existing 1000A 208v 3phase fusible distribution panel. When Calculated I have a I(sc sym rms)=74,426A.
The City planner says that this is an extremely high number and that I need to indicate the Let Thru Current (which I thought was the 74,426A) and need to indicate how I am protecting against this. With every other project I've worked on I have never had any questions in regards to this.
Secondly, He also states that I need to indicate the existing load on existing panels that are gaining circuits. I understand why he would want this(to show that I am not overloading the panels) but how can I figure this out when half the circuits are being removed in the field and most are just receptacle ciruits anyways.
Thank you for any help, I always receive great information from this site.