When calculating the CSR for liquefaction settlement, do you use the normal and total stress after excavation (post-construction) or before excavation?
 
Replies continue below

Recommended for you

Seems you would use whatever stress condition is there at the time of the earthquake.

At least in theory, (N1)60cs shouldn't change much due to unloading by excavation.
 