FSS
Structural
- Sep 24, 1999
- 270
Occasionally I need to print out new sets of plans that have been previously issued and sign/seal them (contractor lost originals or other reasons). As the original sets may have been signed months ago, it seems like something is missing if I just sign with today's date. Should I add a line under the signature saying when the original seal was or something else to that effect? I certainly don't want to give the impression that I have updated the plans (especially if there has been a code change in the interim). What do other folks do in similar cases?