Hello everyone.
I am doing some calculations of a Soil Nail Retaining wall in which the Soil Nails are skewed to 45º.
For the 2D Limit equilibrium calculations I am using the projected length of the anchor (multiplying the length by cos45) and I guess that I should also multiply by cos45 the bond stress and the bar tensile stress so that the program takes into account the proyected force. Am I right?
Many Thanks
Kind Regards