ndjiji
Geotechnical
- Apr 9, 2014
- 25
Hi,
if someone could help me to understand this problem better.
1. For example if i have 8m stiff clay with underlying 10m loose sand.(only example)
The pile will be mainly on skin friction. So let say i want to terminate the pile 9m b.e.g.l (including 8m into stiff clay and 1m into loose sand). is it possible? skin friction will be higher but what about the settlement of pile under loading? because if it is rock, it wont settle that much, but because it is in loose sand, the settlement could be higher although the calculated/mobilised skin friction is higher(??). So should the skin friction pile only terminated in stiff/hard/medium dense/dense layer not in loose sand layer?
2. let say on top of the those layers in problem no.1 is 5m soft clays. So, does it make any different for me to terminate the pile in the stiff clay or still can be terminated in the loose sand layer.
TQ
if someone could help me to understand this problem better.
1. For example if i have 8m stiff clay with underlying 10m loose sand.(only example)
The pile will be mainly on skin friction. So let say i want to terminate the pile 9m b.e.g.l (including 8m into stiff clay and 1m into loose sand). is it possible? skin friction will be higher but what about the settlement of pile under loading? because if it is rock, it wont settle that much, but because it is in loose sand, the settlement could be higher although the calculated/mobilised skin friction is higher(??). So should the skin friction pile only terminated in stiff/hard/medium dense/dense layer not in loose sand layer?
2. let say on top of the those layers in problem no.1 is 5m soft clays. So, does it make any different for me to terminate the pile in the stiff clay or still can be terminated in the loose sand layer.
TQ