mtsnowrider
Civil/Environmental
- Jun 9, 2009
- 3
I'm looking at the feasibility of filling in a concrete structure instead of replacing the rotting floor system. My idea was to fill with gravel and top it with a concrete slab at the existing floor level. The fill is pretty deep though, 17 feet. Even using the most suitable free draining material (3/4" screened rock according to the material supplier) and compacting sufficiently, I would still expect some settlement. If we compact to within 95% of max, if it settles the remaining 5% later that would equate to nearly a foot of settlement. 95% is probably pretty ambitious too considering we have to use a jumping jack. Aside from placing the fill and letting it sit for a year or 2, any ideas on abating the settlement without major structural overhaul?
Thanks
Thanks