Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Slab on grade with drilled pier system

Status
Not open for further replies.

EARK

Structural
May 10, 2023
1
When drilled piers are required and grade beams with foam underneath, is the slab on grade generally to be designed to span between the grade beams?
 
Replies continue below

Recommended for you

Generally Yes. You need to design the slab to span between the grade beams, and the grade beams to span between the drilled shafts. You can pour the concrete against the soil, but over time the soil will settle relative to the shaft supported grade beams.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor