Redacted
Structural
- Mar 12, 2016
- 160
Hi there,
I designed a square manhole 8' wide and total depth including the footing, top slab and grade rings is about 7' max excavation down.
I managed to convince the client to move the manhole further uphill where the water table is not as high, however it may still be present to some degree.
Although its not really my decision on the contractors means and methods, I would like to have an idea in my head how this can play out.
If the contractor excavates down and finds that the water table is about 2' high in the new excavation location, what would be the construction process for :
1) How would you compact the subgrade when constructing in the water table? Instead of trying to compact, would it be better to just excavate down another 1' or 2' and backfill with a 1' or 2' layer of aggregates? I already specified a 4" concrete blinding in the drawings but could use the aggregate as a firm base instead?
2) As for constructing in the water table for a small structure like this, it was mentioned to use diaphragm pumps, which is an option. I was thinking also, what if the contractor built the rebar cage for the foundation on site (where the water table wasn't an issue) and just lifted it in the excavation hole and poured the concrete after? The concrete would displace the water; if the water table is only 2' or so, this may also work?
If the water table is only 1' or 2' up into an excavation do you have any tips or advice to make the construction process easier/simpler?
I designed a square manhole 8' wide and total depth including the footing, top slab and grade rings is about 7' max excavation down.
I managed to convince the client to move the manhole further uphill where the water table is not as high, however it may still be present to some degree.
Although its not really my decision on the contractors means and methods, I would like to have an idea in my head how this can play out.
If the contractor excavates down and finds that the water table is about 2' high in the new excavation location, what would be the construction process for :
1) How would you compact the subgrade when constructing in the water table? Instead of trying to compact, would it be better to just excavate down another 1' or 2' and backfill with a 1' or 2' layer of aggregates? I already specified a 4" concrete blinding in the drawings but could use the aggregate as a firm base instead?
2) As for constructing in the water table for a small structure like this, it was mentioned to use diaphragm pumps, which is an option. I was thinking also, what if the contractor built the rebar cage for the foundation on site (where the water table wasn't an issue) and just lifted it in the excavation hole and poured the concrete after? The concrete would displace the water; if the water table is only 2' or so, this may also work?
If the water table is only 1' or 2' up into an excavation do you have any tips or advice to make the construction process easier/simpler?