X-Wing
Civil/Environmental
- Sep 26, 2012
- 71
The title already said it all: This is a Bridge Project. Single Span. 30m. On RC Piles foundations.
The soil, about 5meters, that was not supposed to be excavated, and that depth, where the piles should be driven, was excavated. I don't know the reason yet.
Given that, they tried to onto the remaining layer, then they were able to drive about 1.5m, and they said it cannot be driven anymore, maybe because it is also refusal.
i've seen the geotech report, at that layer, it is already Coring, with RQD about 10 to 20%.
Any remedies? Piles are supposed to be driven 6m minimum (correct me If im wrong). i'm considering to have a spread foundation. I'll be there tomorrow to inspect.
i Don't know whether the other abutment was already excavated.
Any suggestions? Thanks!
Very Truly Yours,
- andru18
The soil, about 5meters, that was not supposed to be excavated, and that depth, where the piles should be driven, was excavated. I don't know the reason yet.
Given that, they tried to onto the remaining layer, then they were able to drive about 1.5m, and they said it cannot be driven anymore, maybe because it is also refusal.
i've seen the geotech report, at that layer, it is already Coring, with RQD about 10 to 20%.
Any remedies? Piles are supposed to be driven 6m minimum (correct me If im wrong). i'm considering to have a spread foundation. I'll be there tomorrow to inspect.
i Don't know whether the other abutment was already excavated.
Any suggestions? Thanks!
Very Truly Yours,
- andru18