Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Soil pressure diagram behind gravity retaining wall 1

Status
Not open for further replies.

yakpol

Structural
Jun 1, 2001
450
Hello, I have a question for geotechnical engineers. Consider typical reinforced concrete gravity retaining wall, constructed by usual method: 1)excavate behind the heel, 2)construct the wall, 3) Backfill behind the wall.
In case of taller wall (say 15 feet +) and two distinct native soil layers above the footing, would you specify two lateral earth pressure coefficients (and unitweight) or just one. Would it be native soil or backfill parameters.
This is a conceptual question, not based on particular life example.

Thank you for responses!

Yakpol
 
Replies continue below

Recommended for you

Typically, the active soil wedge is going to be completely in the backfill material, so for this case I usually base the earth pressure on one set of soil parameters. However, I have had situations where I used multiple sets of earth pressure coefficients and unit weights.
 
Panars, thank you for reply. I guess it's an open field.
Yakpol
 
In the case you describe, then the geotehncial engineer should provide a pressure diagram since there are just two parameters and the overlying soil unit weight effects the pressure in the lower stratum.

Mike Lambert
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor