I'm working on a design for road widening that will require about 3300 LF of retaining wall, approx 10-25' high. We are evaluating soldier pile vs MSE walls and I need to assess the relative time to construct these walls to factor into the decision.
Option 1 is to furnish soldier piles in drilled shafts with temp. timber laggging and a permanent shotcrete fascia.
Option 2 is to construct an MSE wall with welded wire basket facing.
Any rough estimates of piles per day to compare to square feet or CY of MSE wall per day would be really helpful.