moe333
Geotechnical
- Jul 31, 2003
- 416
Hi all,
I'm working on a conceptual design for a soldier pile wall to retain a 2 lane road approximately 100 feet long. The exposed height of the wall will be about 20 feet. A masonry wall is currently retaining the road and the soldier pile wall would be constructed against the masonry wall, leaving the masonry wall in place. There are no details for the masonry wall. The masonry wall is retaining very moist, medium stiff silty clay/MH fill. The soil below the wall is native, very moist to saturated, stiff silty clay/MH (saprolite) with Su about 2 ksf.
The concept is to drill holes, insert H-beams, and fill the holes with concrete. Lagging would be used between the drilled holes and crushed rock would be used as backfill to provide drainage. Not a lot of experience with designing this type of system so I was looking for suggestions regarding the following:
Pile depth and spacing, type of lagging, pile grouting/concrete, typical H-pile size, wall backfill, any other important considerations?
With this type of system require a tieback or deadman, or will a cantilever be sufficient?
Thanks in advance
I'm working on a conceptual design for a soldier pile wall to retain a 2 lane road approximately 100 feet long. The exposed height of the wall will be about 20 feet. A masonry wall is currently retaining the road and the soldier pile wall would be constructed against the masonry wall, leaving the masonry wall in place. There are no details for the masonry wall. The masonry wall is retaining very moist, medium stiff silty clay/MH fill. The soil below the wall is native, very moist to saturated, stiff silty clay/MH (saprolite) with Su about 2 ksf.
The concept is to drill holes, insert H-beams, and fill the holes with concrete. Lagging would be used between the drilled holes and crushed rock would be used as backfill to provide drainage. Not a lot of experience with designing this type of system so I was looking for suggestions regarding the following:
Pile depth and spacing, type of lagging, pile grouting/concrete, typical H-pile size, wall backfill, any other important considerations?
With this type of system require a tieback or deadman, or will a cantilever be sufficient?
Thanks in advance