Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Solution for fill under an old bridge 1

Status
Not open for further replies.

bridgebridge

Structural
Jun 24, 2011
5
0
0
GB
We have an old single span road bridge which was assessed and considered to be weak. As the railway line under the bridge is dismantled, one of the options is to fill up the structure with fill material and pumped concrete to provide continuous support to the bridge deck. Subsequent to the closure of railway, the bridge has been partially infilled from one side (west side) and a car park has been built on top of the fill and in the level of the road (See attached drawing). So the access to the area under the bridge is only available from the east. We do not have any rights to work from the car park in the west.
We intend to access from the east and dig the fill material 1m in the whole width of the bridge, compact the ground and fill it with concrete.
My question is how can we retain the soil next to the car park from under the bridge with this limited headroom? Any solutions?
Please refer to the attached drawing for more details.
Thanks
 
Replies continue below

Recommended for you

fill it with compacted fill dirt until you loose headroom. Finish the work with open-graded aggregate. Grout from the top when done with filling to obtain intimate support.

There may be other ways and I haven't had my coffee, but that's what comes to mind.

f-d

¡papá gordo ain’t no madre flaca!
 
how is the car park fill supported now? is it a retaining wall? if so, will your excavation on the east side of the wall make this existing wall unstable?

If you need to support this existing car park fill / wall while you are overexcavating, then you may be better off demolishing the bridge anyway
 
It is not clear to me why you wish to dig first. Filling with concrete means you have lots of money for this job. Thus look at other ways, maybe cheaper also.

In that case, there are many different options. I'd explore them before doing what you have planned.

One would be to drill through the deck and then use compaction grouting of the existing fill to compact it somewhat. That would also provide support to the nearby park fill. Chemical grouting is another way to solidify that old fill. This treatment also could wait until all is filled, depending on details.

Getting new fill into the under-deck area then can be by may means. One would be by belt conveyor, such as that used to pile aggregate into piles.

Another way is to use sand and large "conveyor" pipes and compressed air to blow it in there.

Final work would be compaction grouting of what you have placed, with pipes through the deck or pushed in horizontally.

If you still wish to fill with concrete, before you do that, install compaction grout pipes into the existing fill so you can pump in there later. I've even used ordinary downspout pipes for roof drains for this purpose. After concrete has set, go to it to compact that fill under the concrete with injected grout via those pipes. A concrete pump with a sand - cement mix works also. You don't need high pressure for your job.

I am sure others here have some ideas.
 
Thanks for your replies.
The car park fill is not supported now and there is no retaining wall. The fill has a slope of about 45` which goes under the bridge.
The reason we want to dig first is that the fill material is very poor and is mostly rubbish. So we want to dig it first, compact it, and then fill it up to avoid future settlements.
But now I should go through the options oldestguy suggested. In the meantime, I would appreciate other new solutions.
 
Do you have to maintain traffic while doing this? If you could detour traffic and remove the bridge, wouldn't it be much easer? You could also eliminate the bumps at the ends of the bridge.

Maybe the tyranny of Murphy is the penalty for hubris. -
 
If you go with the compaction grouting routine at some stage, I would bet any good grouting contractor will tell you his work will "solidify" that rubbish. After all, if that rubbish is holding the park area now, it will in the future and the grouting will be suitable for eventual bridge support also.

I've seen them do some amazing things, (and some unexpected things, like filling sewers or tilting in basement walls).

Now let's say not everything is done perfectly and eventually the bridge settles or sags in the middle. It probably will not cause an accident, but it likely can be raised with slab jacking methods, should that ever happen.

Get the grouting guy there early for his practical ideas before going further. Be sure to have them furnish references of past good jobs. Not just anybody can do what you will need there.
 
Stay away from sand if possible . If there is any slope it will wash out. You could use any size of aggregate to fill the voids or several different size aggregates then grout. If small aggregate is used you will need grout tubes installed and you will pump from the bottom up. If large aggregate is used and the voids are large enough. You may be able just to drop grout from the top It is possible to get the same strengths as regular concrete using this method.

Intrusion Prepakt /marineconcrete.com
 
Status
Not open for further replies.
Back
Top