bigm
Structural
- Sep 5, 2001
- 2
Have recently poured two 15000 square foot slabs to receive post-tensioning. The owner wished to use sealed bare concrete as a finish on one of the slabs. Cracks were expected but spalling of the cracks occurred also. It was not everywhere but at a lot of places. The worst was about 1-1/2" wide in places and about 1/4" deep. The mix had a lot of fines and the aggregate was as follows: gravel-1550lbs; pea gravel 450lbs; sand 1121lbs; cement 470 lbs.
The cylinders broke very well at 7 days (about 3700 psi). The day was hot, very dry and a 25 mph wind was blowing throughout the days of the pours. The contractor used a plasticizer for the second pour. The slump ranged about 5-1/2" for the first pour and about 7-1/2" with the plasticizer pour. Would the cause of the spalling be more attributable to quick drying of the concrete because of the weather conditions or created by a large number of fines in the concrete. The concrete finish appeared to have been overworked as seen by the swirl finish and a darker gray color. Also small aggregate could be seen at the top of the crack. Thanks for your replies.
The cylinders broke very well at 7 days (about 3700 psi). The day was hot, very dry and a 25 mph wind was blowing throughout the days of the pours. The contractor used a plasticizer for the second pour. The slump ranged about 5-1/2" for the first pour and about 7-1/2" with the plasticizer pour. Would the cause of the spalling be more attributable to quick drying of the concrete because of the weather conditions or created by a large number of fines in the concrete. The concrete finish appeared to have been overworked as seen by the swirl finish and a darker gray color. Also small aggregate could be seen at the top of the crack. Thanks for your replies.