Dennis59
Structural
- Dec 29, 2000
- 56
A question for consulting engineers and specialty design engineers:
A magazine article from November 2000
talked about calculations for specialty engineer-designed items, and how these calculations should be handled by the consultant during the submittal review process. I never saw a follow-up to this article, but I think one is warranted.
Structural examples: wood trusses, cold-formed steel trusses, structural precast concrete, geodesic domes, bridge cranes, etc.
Non-structural examples: fire protection, lightening protection, etc.
Partially-structural examples: wastewater clarifiers, equipment stands, etc.
The consulting engineering firms I have worked for have generally asked for calculations to be submitted along with PE-certified drawings. Once I receive these calculations, I look for the place where the design engineer states his/her design criteria, and I make sure that it matches what I've specified.
My question is: what is the "right thing" to do next? I have heard several approaches over the years:
1) Stop there; your only obligation is to make sure that calculations/drawings are PE-certified and that they claim to have followed your specified criteria.
2) Dig a little deeper and see if the rest of the submittal makes sense - e.g. look for the pages of calculations that are applicable to some of the more critical items and make sure that the specialty engineer's calculations agree with the vendor's drawings.
3) Review everything - calculations and drawings - as if you personally are responsible for the design.
4) Don't even ask for the calculations; you're just opening the door to a lawsuit if something isn't designed right (the thought here, apparently, is that if you don't look at them you can't be held liable).
Let me give you another example:
As I understand this December 1999 newsletter article, someone determined that calculations for wood trusses didn't appear to be correct. After further digging, it was alleged that the specialty engineer PE who was signing off on the design wasn't actually doing what I would consider 'truss design'.
My own personal experience is that more than once I have looked at PE-certified precast and wood truss submittal packages and had to send them back because of one or more of the following:
*calculations and drawings didn't agree
*calculation summary sheet said my criteria was followed, but within the calculations it wasn't really being used
*calculations had errors that were significant enough to cause member size(s) to be changed on the resubmittal
So I am wondering - what, if anything, is the "standard practice of the industry" when it comes to handling a specialty engineer submittal?
More specifically, what is your own personal opinion, and does your opinion agree with that of the firm you work for (if applicable)?
Is this something that may vary from state to state?
Thank you for any response you care to offer.
A magazine article from November 2000
talked about calculations for specialty engineer-designed items, and how these calculations should be handled by the consultant during the submittal review process. I never saw a follow-up to this article, but I think one is warranted.
Structural examples: wood trusses, cold-formed steel trusses, structural precast concrete, geodesic domes, bridge cranes, etc.
Non-structural examples: fire protection, lightening protection, etc.
Partially-structural examples: wastewater clarifiers, equipment stands, etc.
The consulting engineering firms I have worked for have generally asked for calculations to be submitted along with PE-certified drawings. Once I receive these calculations, I look for the place where the design engineer states his/her design criteria, and I make sure that it matches what I've specified.
My question is: what is the "right thing" to do next? I have heard several approaches over the years:
1) Stop there; your only obligation is to make sure that calculations/drawings are PE-certified and that they claim to have followed your specified criteria.
2) Dig a little deeper and see if the rest of the submittal makes sense - e.g. look for the pages of calculations that are applicable to some of the more critical items and make sure that the specialty engineer's calculations agree with the vendor's drawings.
3) Review everything - calculations and drawings - as if you personally are responsible for the design.
4) Don't even ask for the calculations; you're just opening the door to a lawsuit if something isn't designed right (the thought here, apparently, is that if you don't look at them you can't be held liable).
Let me give you another example:
As I understand this December 1999 newsletter article, someone determined that calculations for wood trusses didn't appear to be correct. After further digging, it was alleged that the specialty engineer PE who was signing off on the design wasn't actually doing what I would consider 'truss design'.
My own personal experience is that more than once I have looked at PE-certified precast and wood truss submittal packages and had to send them back because of one or more of the following:
*calculations and drawings didn't agree
*calculation summary sheet said my criteria was followed, but within the calculations it wasn't really being used
*calculations had errors that were significant enough to cause member size(s) to be changed on the resubmittal
So I am wondering - what, if anything, is the "standard practice of the industry" when it comes to handling a specialty engineer submittal?
More specifically, what is your own personal opinion, and does your opinion agree with that of the firm you work for (if applicable)?
Is this something that may vary from state to state?
Thank you for any response you care to offer.