telecomguy
Mechanical
- Jan 4, 2006
- 274
I have some components that were downloaded and/or generated without ECAD interface in mind. The default coordinate system is not located/oriented properly. So I have added an additional CSYS that matches our Mentor database components. The export from ProE to Mentor works great because I can select the alternate CSYS during the export process.
But when the CAD guys send me an EMN/EMP export from Mentor and I pull it into ProE the parts get placed based on the original default CSYS and not my alternate CSYS.
How/where do I specify the mapping (I intentionally used that word because that's where I would expect to do it) to my new CSYS? Or is it one of those 'magic name' situations where I need to rename my CSYS to some special name that is not documented anywhere but the import process knows about?
Thanks,
<tg>
Please see FAQ731-376 before flagging posts. Per line item #4, some cross posting is appropriate when done correctly.
But when the CAD guys send me an EMN/EMP export from Mentor and I pull it into ProE the parts get placed based on the original default CSYS and not my alternate CSYS.
How/where do I specify the mapping (I intentionally used that word because that's where I would expect to do it) to my new CSYS? Or is it one of those 'magic name' situations where I need to rename my CSYS to some special name that is not documented anywhere but the import process knows about?
Thanks,
<tg>
Please see FAQ731-376 before flagging posts. Per line item #4, some cross posting is appropriate when done correctly.