johndeng
Structural
- Mar 6, 2012
- 120
We need grating to cross span 8', but the contractor only makes 3'x4' grating, so we'll need to put(2)w10x12 splice below. w10x12 splice beams are at each side. w10x12 will have to take all the middle span moment, welding between the grating and w10 will make them composite beyond middle splice. However I am only able to put beams each side of the grating, and weld only one side of the beam to the grating at side edge.
any comments?
any comments?