grad225
Civil/Environmental
- Aug 4, 2011
- 1
I have a model of a bridge that I'm recreating in Abaqus from a Load Test and Rating Report. The report states that they employed linear and rotational springs for the supports; however when I put these in Abaqus with the spring constants specified in the report, I am getting an error. "Too many attempts made for this increment"
Is there any way I can fix this or is there something else I have to add in the BCs in addition to the springs?
Thanks!
Is there any way I can fix this or is there something else I have to add in the BCs in addition to the springs?
Thanks!