Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

SPT Borehole Diameter Correction Factor

Status
Not open for further replies.

NBRY1

Civil/Environmental
Dec 7, 2016
56
0
0
US
Given that SPT is not an exact science:
Should one apply a borehole diameter correction factor, CB (other than 1.0) when determining the N60 value, if mud-rotary methods are used?
My understanding is that it is used to account for stress relief in the larger diameter borings due to overburden removal.
 
Replies continue below

Recommended for you

It used to be considered good practice to apply the assumed corrections over a range of expected depths, soil/soft rocks, drilling process/medium and sampling equipment/personnel. Then consider what is actually being accomplished and/or learned. Most of these answers come during the application process.
 
The correction factor for size increases at 6 inches. Mud rotary is usually less than 6 inches so the correction factor of 1 is appropriate.
 
Status
Not open for further replies.
Back
Top