Hi all,
I am currently calculating SPT uncorrected N values for a variation of soils. I am getting a first 150 mm value (say 25 blows) fine which i understand you disregard. However i will get another 150 mm value (say 30 blows) but refusal thereafter. Will my N value therefore be 30? Also i have 150 mm value of 25 then the next value is 30 for 100 mm penetration. Is there a correction or calculation you have to undertake to utilise this value?
Cheers for any advice.
I am currently calculating SPT uncorrected N values for a variation of soils. I am getting a first 150 mm value (say 25 blows) fine which i understand you disregard. However i will get another 150 mm value (say 30 blows) but refusal thereafter. Will my N value therefore be 30? Also i have 150 mm value of 25 then the next value is 30 for 100 mm penetration. Is there a correction or calculation you have to undertake to utilise this value?
Cheers for any advice.