Paulettaa
Mechanical
- Mar 17, 2018
- 60
Dear All
Please help me understand something regarding SPWHT of SA-516 70.
In the engineering spec. of the project it is mentioned that where PWHT is required the mill certificate is required for three cycles of PWHT. Does this mean that I have to sent test coupons to a laboratory and ask them to verify if mechanical requirements after three cycles of PWHT is acceptable as per the corresponding material spec.? Or is it necessary that this test be done by the manufacturer of the plate?
Other question is that when they mention minimum three cycles of PWHT, does it imply three heating, holding, and cooling procedures the same as those expected in real PWHT or just on heating, holding, and cooling with a time three times that of real situation?
The thickness of material is 75mm and 45mm if it helps.
Warm Regards
Please help me understand something regarding SPWHT of SA-516 70.
In the engineering spec. of the project it is mentioned that where PWHT is required the mill certificate is required for three cycles of PWHT. Does this mean that I have to sent test coupons to a laboratory and ask them to verify if mechanical requirements after three cycles of PWHT is acceptable as per the corresponding material spec.? Or is it necessary that this test be done by the manufacturer of the plate?
Other question is that when they mention minimum three cycles of PWHT, does it imply three heating, holding, and cooling procedures the same as those expected in real PWHT or just on heating, holding, and cooling with a time three times that of real situation?
The thickness of material is 75mm and 45mm if it helps.
Warm Regards