Inspector807
Specifier/Regulator
- Jul 3, 2002
- 11
A slab was poured and was a good bit out of square, at one point it went from 6"s to about 10"s the concrete ment dug down beside the monolithic slab 12" deep and as wide as they needed to resquare the slab, the new concrete was not tied to the existing slab, my question is was it supposed to be or will it hold up being done like this, the ext wall was of 2x4 construction and load bearing, what is the appropriate fix for monolithic slabs that are poured so out of square, thank you