Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Standards/guidelines for piping layout design to separate fluid types by hazard 1

Status
Not open for further replies.

matt1979

Chemical
Jul 13, 2006
3
Hi everyone,

Currently looking at 3 process pipelines (sulphuric acid, ammonia and high pressure steam) being run beside each other. Is there any international piping/layout standards that recommends separation of dissimilar fluids in pipe racks to mitigate potential hazards in the event of a pipe-break?

Thanks in advance,

M
 
Replies continue below

Recommended for you

Dear matt1979,

The services you have mentioned are pretty common in oil and gas plants and these piping have existed beside each other for more than half a century without any conflict.

Regards.

DHURJATI SEN
 
Yes, three process lines as stated can be placed together in the same level of pipe rack if the space is available. Typically, the process lines are grouped in the lower level(s) of pipe rack to keep the routing short and neat. The utility lines, on the other hand, are routed later and using the upper levels. And, keep the larger bore pipes closer to the pipe rack columns, and small lines can be located in the middle section.
 
No such international overall pipe system routing guide exists.

I agree with the responses above ....

You have to understand how difficult it would be to develop such a guideline for the thousands of combinations of chemical processing systems.

Process Safety of hazardous piping systems is developed by:

1) Ensuring that the most up-to-date engineering design installation, and testing guidelines FOR THE PARTICULAR SYSTEM is being followed (e.g. no threaded joints in oxygen or ammonia piping)

2) Ensuring that a comprehensive fire hazard review FOR THE PARTICULAR PLANT SITE has been performed

3) Ensure that a comprehensive HAZOP evaluation has been performed for the entire plant

4) Ensure that plant REPAIR AND MAINTENANCE PRACTICES have been reviewed for safety.

My opinion only ....

MJCronin
Sr. Process Engineer
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor