OilBoiler
Chemical
- Aug 5, 2003
- 43
Hey everyone,
I'm designing a control scheme at which I would like to "start" a pH controller after a level has been reached in the tank, since this is a semi-batch process. I won't be doing the loop drawings for the project, but I need to know whether this is feasible? Because I don't need the pH controller to be acting all the time. I only need it to open or close valves once the tank has filled and then stop acting when the low level is reached.
Thanks in advance!
I'm designing a control scheme at which I would like to "start" a pH controller after a level has been reached in the tank, since this is a semi-batch process. I won't be doing the loop drawings for the project, but I need to know whether this is feasible? Because I don't need the pH controller to be acting all the time. I only need it to open or close valves once the tank has filled and then stop acting when the low level is reached.
Thanks in advance!