sshep
Chemical
- Feb 3, 2003
- 761
My Friends,
We have a 400psi steam line routed across a public road with 20ft clearance. We need 45ft of clearence to pass equipment underneath for a new project. Our E&C contractor wants to reroute it underground.
I have seen alot of lines routed below roads through culverts in the plant- i.e. piping can be easily trapped out and low spots accessed, the only real problem was pumping out rainwater, which we did via air lift pump in the plant.
Under this road the line would either be buried which I have never seen and might have its own problems; or through a culvert in which case I would worry about draining rainwater and restricting public access, etc.
Any ideas or advice?
best wishes,
sshep
We have a 400psi steam line routed across a public road with 20ft clearance. We need 45ft of clearence to pass equipment underneath for a new project. Our E&C contractor wants to reroute it underground.
I have seen alot of lines routed below roads through culverts in the plant- i.e. piping can be easily trapped out and low spots accessed, the only real problem was pumping out rainwater, which we did via air lift pump in the plant.
Under this road the line would either be buried which I have never seen and might have its own problems; or through a culvert in which case I would worry about draining rainwater and restricting public access, etc.
Any ideas or advice?
best wishes,
sshep