271828
Structural
- Mar 7, 2007
- 2,267
Some of you will think these are pretty funny questions, but I'll ask it anyway. I've been wondering about these for a while.
Say I have a bolted-bolted dougle angle connection with bolts in-line rather than staggered. Folks often use L4x4x5/16 with a 2-11/16" angle gage in each leg of each angle. This is no good according to the 13th Ed. Table 7-16 with "no good" being defined ask not being able to get a socket on either bolt.
So what's the deal here? Do erectors just use a wrench for these situations, so it doesn't matter if Table 7-16 is violated? If that's the case, then what's the use of Table 7-16?
While I'm at it: What are the common angle sizes and gages that you guys see for this type of connection?
When this kind of connection is made to a girder, I've heard it referred to as a "suicide connection" because the first installed beam must somehow be supported without bolts while hte second is installed. Is there a standard procedure for dealing with this issue? I've seen people show temporary seats at some connections, but don't know if this is mandatory. Commentary on this would be appreciated.
Thanks in advance.
100000e
Say I have a bolted-bolted dougle angle connection with bolts in-line rather than staggered. Folks often use L4x4x5/16 with a 2-11/16" angle gage in each leg of each angle. This is no good according to the 13th Ed. Table 7-16 with "no good" being defined ask not being able to get a socket on either bolt.
So what's the deal here? Do erectors just use a wrench for these situations, so it doesn't matter if Table 7-16 is violated? If that's the case, then what's the use of Table 7-16?
While I'm at it: What are the common angle sizes and gages that you guys see for this type of connection?
When this kind of connection is made to a girder, I've heard it referred to as a "suicide connection" because the first installed beam must somehow be supported without bolts while hte second is installed. Is there a standard procedure for dealing with this issue? I've seen people show temporary seats at some connections, but don't know if this is mandatory. Commentary on this would be appreciated.
Thanks in advance.
100000e