Charred
Structural
- Jan 29, 2016
- 35
I have a unique project where the SFRS will be steel special moment frames. (SDC D and architectural constraints do not allow for braced frames. On one side of the building, the finish grade is extremely high and will require a heavy concrete retaining wall. I planned to have the SMF columns at that side be supported by reinforced concrete pilasters. See attached elevation. However, in reviewing ASCE 7-10 Section 12.2.5.5 states 'Where a special moment frame is required by Table 12.2-1, the frame shall be continuous to the base.' Does this requirement mean I have to take the SMF columns all the way to the ground floor like the other columns? Or can I designate the top of the pilasters as the base in this condition? If I have to take the SMF columns to the base, I would need to modify the architect's floor layout and push the wall far enough away so my columns can pass by.