I am going to have sewer constructed with directional drilling at grade increasing all the way to 70%! It will be a 6 inch with commercial flow from a 911 center..i.e not much flow. I do not see much of an issue although some engineers say there is a max flow for solids seperation...We flush line once a year although this line will be flush in reverse due to grade.
Commnets?
I am going to have sewer constructed with directional drilling at grade increasing all the way to 70%! It will be a 6 inch with commercial flow from a 911 center..i.e not much flow. I do not see much of an issue although some engineers say there is a max flow for solids seperation...We flush line once a year although this line will be flush in reverse due to grade.