zlr219
Structural
- Jun 2, 2004
- 2
We are considering using a ribbed mat slab for a Pre-engineered metal building. I don't have the loads, but would expect about 10 kips net uplift at approximately 25 foot bay spacing. Does the PTI/WRI methods account for this type of loading? I feel that piers are in order, but the contractor wants to save, save, save.