I am designing a fix for a 5,000 s.f. or so patio in a flood plain. The patio is built up 3-4 feet above the ground and is settling relative to the adj building (which is on piles) about 6-8 in.
The patio surface is brick pavers - which I can remove and regrade, but there are two problems: 1) The ground will likely continue to settle, and 2) There is a storm MH in the patio which has settled the same amount as the patio (the rim is even with the settling pavers) and I've got 'sinkholes' in line with the storm pipes from the MH. Looking in the MH, the pipes are becoming disconnected from the MH.
Any suggestions? Is there a flexible product I can re-connect the storm pipes with? Should I plan on re-building the patio every few years?
The patio surface is brick pavers - which I can remove and regrade, but there are two problems: 1) The ground will likely continue to settle, and 2) There is a storm MH in the patio which has settled the same amount as the patio (the rim is even with the settling pavers) and I've got 'sinkholes' in line with the storm pipes from the MH. Looking in the MH, the pipes are becoming disconnected from the MH.
Any suggestions? Is there a flexible product I can re-connect the storm pipes with? Should I plan on re-building the patio every few years?