Thom93
Civil/Environmental
- Sep 27, 2010
- 5
I will start off with a hypothetical example, and then ask my questions rearding stormdrain design procedures.
The hypothetical example is this: there is a single storm drain system with a single on-grade inlet at it terminus. The inlet bypasses offsite. The drainage area to the inlet is large; the runoff is 100 cfs by the Rational Method only. However, the inlet is small; its capacity is only 2 cfs. The remainder, 98 cfs, bypasses the inlet and goes off-site. This is the only information that is given, so the Tc, gutter cap., intensity, runoff coeff., design storm, etc...is not important to the example.
Ordinarily, you would go through an inlet sizing and spacing exercise, but in this example, we cannot. The inlet will pick up 2 cfs under all conditions.
Now, according to HEC-22 and AASHTO Drainage Design Criteria, the assumption is that the storm drain system picks up all of the drainage basin. There is no inlet bypass in the storm drain design. All of the basin contributes and I have to size my system for 100 cfs. StormCAD and Hydroflow Storm Sewers will do the same thing; they will size a storm pipe for 100 cfs. HEC-22 stresses the importance of Tc, so as you move through the system, your Tc increases, Intensity decreases, Q decreases, etc...
You can set the programs to use only inlet captured flows, however. If you use inlet captured flow, the Q will be 2 cfs, but the Tc will not change. Try it yourself. space 3-4 inlets on grade and use inlet captured flows only and you'll find that the system will just "add up" the Qs and Tc will remain the same throughout the system.
So, here's the question: what would be the correct method?
Using HEC-22 does not seem intuitively correct because the inlet can only pick up 2 cfs. What happens to the bypass? It doesn't flow down and enter the system downstream; it all gets in the inlet using HEC-22 and so the pipe would have to be very large.
Using inlet captured flows seems correct, because the pipe can be very small and the bypass can just get into the system at the next inlet, but this is not the correct "procedure". It is not technically correct per HEC-22.
I don't need to know how to design storm systems, I just want to know how others have handled situations where inlet bypass kept accumulating downstream.
Thanks.
The hypothetical example is this: there is a single storm drain system with a single on-grade inlet at it terminus. The inlet bypasses offsite. The drainage area to the inlet is large; the runoff is 100 cfs by the Rational Method only. However, the inlet is small; its capacity is only 2 cfs. The remainder, 98 cfs, bypasses the inlet and goes off-site. This is the only information that is given, so the Tc, gutter cap., intensity, runoff coeff., design storm, etc...is not important to the example.
Ordinarily, you would go through an inlet sizing and spacing exercise, but in this example, we cannot. The inlet will pick up 2 cfs under all conditions.
Now, according to HEC-22 and AASHTO Drainage Design Criteria, the assumption is that the storm drain system picks up all of the drainage basin. There is no inlet bypass in the storm drain design. All of the basin contributes and I have to size my system for 100 cfs. StormCAD and Hydroflow Storm Sewers will do the same thing; they will size a storm pipe for 100 cfs. HEC-22 stresses the importance of Tc, so as you move through the system, your Tc increases, Intensity decreases, Q decreases, etc...
You can set the programs to use only inlet captured flows, however. If you use inlet captured flow, the Q will be 2 cfs, but the Tc will not change. Try it yourself. space 3-4 inlets on grade and use inlet captured flows only and you'll find that the system will just "add up" the Qs and Tc will remain the same throughout the system.
So, here's the question: what would be the correct method?
Using HEC-22 does not seem intuitively correct because the inlet can only pick up 2 cfs. What happens to the bypass? It doesn't flow down and enter the system downstream; it all gets in the inlet using HEC-22 and so the pipe would have to be very large.
Using inlet captured flows seems correct, because the pipe can be very small and the bypass can just get into the system at the next inlet, but this is not the correct "procedure". It is not technically correct per HEC-22.
I don't need to know how to design storm systems, I just want to know how others have handled situations where inlet bypass kept accumulating downstream.
Thanks.