Concreter
Civil/Environmental
- Nov 27, 2003
- 1
Hello,
My company is building a 5000 sq m concrete slab for a steel recycling yard to put their -outdoor- stockpile on.The pile grows to approx 10000 tonnes before being shipped out.
All runoff goes to one point at which I am looking at a sand trap for oil and some kind of filter for rust colour.
Any ideas are welcome - I'm trying to keep the system as simple as possible so that maintenance by the scrapyard workers is easily done.Discharges to local stream.