We are installing an RO to let down the pressure downstream of a control valve. Since we are only taking a pressure drop and not taking flow measurements, is it necessary to have straight run requirements?
 
Replies continue below

Recommended for you

skuntz,
No, if you are not measuring then you do not need any straight run.