We are replacing stress cones on a 35kV system as a result of a recent cable fault. During the installation of the new cones it was sugessted to add heat shrink overlapping the the new stress cone covering the ground braid completely. In my experience I have never seen this done and I am a little concerned of any long term effect this may have on the new cones. Can anyone comment if this is common pratice or if there are any long term effects by doing so.