Contractor requests to go for VS4 type vertical submersible pump instead of earlier proposal of Submersible pump as the zone classification of these lift stations are now considered to be one 2. They say that submersible pump motors cannot be made suitable for Hazardous zone.
Is it agreeable to accept the contractor proposal so that the motor is complied with the required classification?
Thanks in advance for your reply
Is it agreeable to accept the contractor proposal so that the motor is complied with the required classification?