JAE
Structural
- Jun 27, 2000
- 15,463
We recently designed a small addition to an existing sewage treatment facility that involved a deep (20 ft) concrete vault situated next to an existing pumphouse/vault. Both the existing and the new vault are set on a thick floor mat of concrete at the same elevation. The geotech gave us design guidance that was followed and the contract was bid.
On the contract plans, we included boring logs from the geotech report for information only. The contractor who won the bid assumed that he could successfully cut his excavation vertically the 20 feet around the vault addition and shore this excavation with a soldier pier wall system. He saw on the boring logs that from 20 ft. to 30 ft. was a "hard" lean clay that should adequately hold his piling/piers.
Now that he has begun driving his piling, he has discovered that the actual soil conditions seem to be different - once the piling hits 25 feet, the piling takes off downward through a very soft material. He now believes that he cannot use soldier piers and must lay back the excavation.
Our specs say that he cannot rely on the soil data and then hold the owner for extra costs based on that reliance. This is what we agree as well.
Our concept is based on an important distinction:
1. If the contractor finds bad soil and this requires a change in the DESIGN of the structure, then he should be compensated for those changes and time costs.
2. BUT, if the contractor makes an assumption of soil quality that affects his MEANS AND METHODS of building the structure, then he is taking his own risk.
Do you think this distinction is consistent with "standard" industry practices? (the project is in the U.S.)
On the contract plans, we included boring logs from the geotech report for information only. The contractor who won the bid assumed that he could successfully cut his excavation vertically the 20 feet around the vault addition and shore this excavation with a soldier pier wall system. He saw on the boring logs that from 20 ft. to 30 ft. was a "hard" lean clay that should adequately hold his piling/piers.
Now that he has begun driving his piling, he has discovered that the actual soil conditions seem to be different - once the piling hits 25 feet, the piling takes off downward through a very soft material. He now believes that he cannot use soldier piers and must lay back the excavation.
Our specs say that he cannot rely on the soil data and then hold the owner for extra costs based on that reliance. This is what we agree as well.
Our concept is based on an important distinction:
1. If the contractor finds bad soil and this requires a change in the DESIGN of the structure, then he should be compensated for those changes and time costs.
2. BUT, if the contractor makes an assumption of soil quality that affects his MEANS AND METHODS of building the structure, then he is taking his own risk.
Do you think this distinction is consistent with "standard" industry practices? (the project is in the U.S.)