Ingenuity
Structural
- May 17, 2001
- 2,370
Curious what amount/quantity of horizontal rebar you typically provide in a concrete upturn parapet that is poured AFTER placement of the roof slab, say 100 feet long, zero vertical joints?
I have a case of an existing (2 year old) 8+" wide x 15" high parapet (rather squat) with cracks every 4 feet. 3#4 horizontal bars in the center of wall were provided by the EoR. Amounts to 0.44% rebar.
Given the significant bottom slab restraint, the drying shrinkage cracks have telegraphed through the exterior finish (elastomeric-ish paint) and resulting in an upset building owner.
Curious what other engineers provide for such parapets (or a high curb in this instance)?
My guess is hokie66 will say "more than 0.6%"