ataman
Structural
- Dec 7, 2006
- 53
Hi
I have a situation where a recently poured suspended slab has some severe cracking in my opinion. The cracks are fairly long and straigt and generally intersect perpendicular to each other. There are however some cracks which are random is length and direction. Some of the larger cracks I can push a quater halfway down the crack and a bit of tying wire 2" into the 6" slab.
The conctractor has taken some cores for testing but believes that the cracks are plastic shrinkage cracks. I agreed the they could be since the concrete was poured in hot weather. I was thinking that there must have been too much water added to the concrete which caused the significant drying shrinkage cracks but the contractor insists that it isn't. The contractor is also a civil engineer.
My thoughts to the client is that the slab should be removed and redone especially since it is a suspended slab. The conctractor wants to wait for the test results and if the strength is ok suggests that we keep the slab. He is also willing to do a load test.
The slab is an indoor slab so it will not be exposed to the elements.
Any thoughts on this?
Thanks
I have a situation where a recently poured suspended slab has some severe cracking in my opinion. The cracks are fairly long and straigt and generally intersect perpendicular to each other. There are however some cracks which are random is length and direction. Some of the larger cracks I can push a quater halfway down the crack and a bit of tying wire 2" into the 6" slab.
The conctractor has taken some cores for testing but believes that the cracks are plastic shrinkage cracks. I agreed the they could be since the concrete was poured in hot weather. I was thinking that there must have been too much water added to the concrete which caused the significant drying shrinkage cracks but the contractor insists that it isn't. The contractor is also a civil engineer.
My thoughts to the client is that the slab should be removed and redone especially since it is a suspended slab. The conctractor wants to wait for the test results and if the strength is ok suggests that we keep the slab. He is also willing to do a load test.
The slab is an indoor slab so it will not be exposed to the elements.
Any thoughts on this?
Thanks