sykimk
Electrical
- Dec 28, 2003
- 55
Hello,
I will do commissioning tests for a plant synchronization system to control a group of turbine generators (2 ~ 3 generators together) to be synchronized onto the grid. FYI, GE CTG rating: 40 MW & Siemens STG rating: 82 MW. For our system, at least 1xCTG, and 1xSTG are to be controlled together for generation bus synchronization with the grid. Of course, the generation bus with multiple generators runs in island mode.
To me, this situation would be quite challenging since CTG & STG controller's responses are not the same. So, I am really concerned if this synchronization would really work although it would take a quite long time.
Do you have any experiences with the synchronization of multiple generators onto the grid? Do you have any thoughts and/or advice? Anything will be very helpful for me.
Thanks in advance.
I will do commissioning tests for a plant synchronization system to control a group of turbine generators (2 ~ 3 generators together) to be synchronized onto the grid. FYI, GE CTG rating: 40 MW & Siemens STG rating: 82 MW. For our system, at least 1xCTG, and 1xSTG are to be controlled together for generation bus synchronization with the grid. Of course, the generation bus with multiple generators runs in island mode.
To me, this situation would be quite challenging since CTG & STG controller's responses are not the same. So, I am really concerned if this synchronization would really work although it would take a quite long time.
Do you have any experiences with the synchronization of multiple generators onto the grid? Do you have any thoughts and/or advice? Anything will be very helpful for me.
Thanks in advance.