JustinMKN
Computer
- Sep 12, 2006
- 1
Not sure if anyone has any experience with this. Here is my senario I'm trying to transfer information from the "Gantt Chart" view to the "Resource Usage Sheet". Specifically all of the tasks have a unique identification number used in another report ( A 5 digit number ). Typically the managers use the Resource Usage sheet to update hours etc for each person on each project. But they need this Unique Identification number to align things. Right now all they can see is the project name under the resource, I cant get any other information from the Gantt View to transfer over. Their seems to be some kind of invisible barrier. Any help would be awesome.