Is there a view where you can see all the tasks not assigned? I'm not referring to the gantt chart view. I'm referring to a view where you only see the tasks that haven't been assigned. Something that shows the project name and tasks not assigned yet.
 
Replies continue below

Recommended for you

Are you talking about MS project?

This is a general project management forum so you'll need to clarify.

I'm not sure if there is a specific project forum under
KENAT, probably the least qualified checker you'll ever meet...
 
The OP knows where it is, since he's posted there before.

Have you looked at the Resource Usage View? The first set of items are the unassigned tasks.