kechha2060
Civil/Environmental
- Dec 8, 2007
- 26
My roadway is being constructed in a fill embankment. Construction sequence is proposed to construct half width at a time. Temporary shoring is proposed to protect the embanked roadway (12' higher than existing). While doing the second half how would the required compaction at/near the shoring attained and how is that shoring pulled out? Do anyone share their experience?
Thanks
proposed roadway
-------------------
|
|
|<----- Temporary shoring
|
|
| existing roadway
------------------------
Thanks
proposed roadway
-------------------
|
|
|<----- Temporary shoring
|
|
| existing roadway
------------------------