Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Temperature and Shrinkage Reinforcement in strip footing

Status
Not open for further replies.

gijaja

Structural
Nov 5, 2009
1
In a strip footing of a cantilever retaining wall, is one
layer of Temp and Shrinkage in the long direction sufficient? Are there any requirements for T&S in both the top and bottom?
 
Replies continue below

Recommended for you

T&S (temperature and shrinkage) reinforcement is required for the total cross section. So if you have a cantilever retaining wall footing 10-12" thick, I generally provide 1 layer of #5 bars at 12". This makes up the required 0.2% which constitutes minor crack control.

See attached.
 
 http://files.engineering.com/getfile.aspx?folder=eb22fb57-2adc-4a64-bb97-808a6a489f3c&file=CANT_RETAINING_WALL.jpg
Yes. I typically provide one layer bottom at the toe, just over the toe steel, and one layer top in the heel, just under the heel steel.

Mike McCann
MMC Engineering
Motto: KISS
Motivation: Don't ask
 
It isn't exempted in the ACI 318, perhaps slab on grade or somewhere else? I don't recall putting in that much steel for T&S. The temperature isn't an issue since the footing is always buried, so it's only shrinkage.

Albeit I admit its been years since I designed a concrete retaining wall, and 90% of the time I'd just use a State standard plans. I only designed walls when there was an anomaly, property line, unusual soil condition, etc.

Also the cost of the steel is usually not an issue, so I recommend put it in if you have any doubt.
 
Do any of you provide joints in the footing that match the wall joints, ie 6-8m centres? And do you have the footing pours sequenced so alternate strips are poured?
 
Depends if the footing slab is visible. If the slab is not visible then I just specify a continuous run of footing without any joints. If the footing slab is visible (say it also serves as a pavement) then I will specify that the slab joints match the wall joints.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor