dcdtn
Electrical
- Jan 23, 2003
- 28
I am wanting to parallel a 150MVA with a 250 MVA transformer (both 161-46-kV) temporarily in the event that one needs to be taken out for maintenance. Normally, one bank is heavily loaded and the other lightly loaded and the 46-kV bus is split. My first question is what type of switch is needed to join the 46-kV buses, thus initiating the parallel operation. The second question is how long can these banks be operated in this temporary ,paralleled configuration. My last question is what type of switch is needed to deenergize one of the banks from the 46-kV side once the 161-kV breaker is opened (there is no breaker on the 46-kV side). Thanks in advance.