Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations Toost on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

The 2 drivers of an Oil & Gas Project duration

Status
Not open for further replies.

HerveBaron

Petroleum
Jun 1, 2015
1
Project Critical Path (CP) law
“The time it takes to build an Oil & Gas facility is the time it takes to build its pipework. Pipework construction effectively starts once engineering is nearly completed. Engineering effectively starts 2 months after half the equipment have been ordered.”

Project Duration (PD) law
“The duration of piping construction cannot be reduced below a certain minimum deriving from the facility’s piping tonnage. The duration of engineering cannot be reduced below a certain minimum deriving from the number of engineering manhours”.

You will find more details in the attachment.
 
 http://files.engineering.com/getfile.aspx?folder=a2f35eb6-b8aa-49c2-992c-334470e36b2f&file=Laws.pdf
Status
Not open for further replies.

Part and Inventory Search

Sponsor