This is simple, and you will want to know this to avoid possible litigation down the road. That's what really matters, right? You can not adversely impact the historical discharge point, or adversely affect the capacity down stream of the historical discharge point. So you will want to sufficiently attenuate your developed release rate by providing adequate detention storage volume to do so.
This is simple, and you will want to know this to avoid possible litigation down the road. That's what really matters, right? You can not adversely impact the historical discharge point, or adversely affect the capacity down stream of the historical discharge point. So you will want to sufficiently attenuate your developed release rate by providing adequate detention storage volume to do so.